news
Thursday, November 19, 2026

Modules on the move: a major milestone for cable materials on Sweden’s west coast

Three large modules have been transported and installed at our Stenungsund site, marking a key milestone in our project to expand production of medium-voltage cable insulation materials in Sweden.

Three enormous, prefabricated modules are now in place at our site in Stenungsund, on Sweden’s west coast. They form part of a new production unit that will increase our capacity to produce cross-linked polyethylene (XLPE) compounds for medium-voltage power cable insulation.

The modules, the largest of which is 24 meters high, were built at our project partner Bilfinger’s construction area, just across the road from our site. Meanwhile, the project team prepared the ground and foundations.

Once complete, each module was loaded onto two self‑propelled modular transporters. Travelling at just 1–3 kilometers per hour, they carried the modules across the road to the prepared installation area. The move required the road between the two facilities to be closed for four consecutive nights in early October so the oversized loads could be transported safely.

Slow but steady: the modules make their way to the installation area at just 1-3 km/h, © Borouge International
Slow but steady: the modules make their way to the installation area at just 1-3 km/h, © Borouge International
Heavy haulage in action: the completed module being transported to the installation area on a self-propelled modular transporter, © Borouge International
Heavy haulage in action: the completed module being transported to the installation area on a self-propelled modular transporter, © Borouge International

Installation was carried out using a huge crane with a 117-meter boom. The crane itself had to be delivered in sections and assembled on site. The team used it to lift the modules into place and assemble the new tower, which stands 58 meters high. The final stage was installing the elevator sections, which had to wait until the weather was calm enough for the crane to lift them safely into place.

Precision at height: a 117-meter boom crane positions a tower module for assembly, © Borouge International
Precision at height: a 117-meter boom crane positions a tower module for assembly, © Borouge International

A carefully planned operation

Planning for this operation began on day one of the project, back in April 2025. The team carefully coordinated each stage, with safety the first priority.

“Getting to this point has taken months of detailed preparation and close cooperation between the teams involved,” explains Knut Lia, Senior Project Manager at KANFA. “That same attention to detail throughout the project has helped us reach more than 270 days without a recordable injury – an achievement everyone working on the project can be proud of.”

Early site preparations also involved some less familiar team members. Before groundwork began, two specially trained detection dogs and their handlers surveyed the area to check for remnants from past blasting activities.

Safety first: specially trained detection dogs inspected the site for remnants of past blasting activities before construction began, © Explosivhund Miljö & Säkerhet Sverige AB
Safety first: specially trained detection dogs inspected the site for remnants of past blasting activities before construction began, © Explosivhund Miljö & Säkerhet Sverige AB

A different way of building

This project is being carried out together with KANFA through an engineering, procurement and construction (EPC) turnkey contract. This means KANFA is coordinating engineering, procurement and construction, including the work of subcontractors on site.

“This expansion involves building a new, separate unit that will be connected to our existing facilities, making it well suited to a turnkey approach,” explains Louise Andersson, Asset Development Manager at Borouge International’s Stenungsund site. “Having one knowledgeable and experienced partner responsible for the entire delivery helps streamline the work, but it makes the preparation stage especially important. The scope and requirements need to be clearly defined at the outset, with progress monitored closely throughout the project.”

Supporting the European energy transformation

This investment in Stenungsund is part of “Building for the Future” — our EUR 200 million commitment to upgrade and expand XLPE and semiconductive cable material production at key European sites.

The insulation materials produced in the new unit will be used to manufacture medium-voltage cables. These cables distribute electricity to local communities and industrial sites, and connect renewable energy installations to the grid. As more sectors shift toward electrification, electricity demand is growing and many of these networks need to be expanded and upgraded.

“Expanding electricity networks requires investment throughout the supply chain,” says Davide Vielmi, VP Global Marketing Energy at Borouge International, formerly Borealis. “By increasing our production capacity in Stenungsund, we’re helping our customers access the materials they need to support the energy transformation.”

Modules on the move: a major milestone for cable materials on Sweden’s west coast | Borouge International